Updated renovation schedule (10/15/07 to 12/31/08)
The hotel would like to revise the announcement letter for your reference. There are some changes from the previous announcement as follows;
1. The construction period is changed to 5 October 2007 for 15 months, due to the contractors are unable to start the construction on September as per previous announcement.
2. During Peak season (20 December 07 until 10 January 08), the construction will be stopped in order not to disturb the guests during their stay. The construction will start again on 11 January 08.
3. Most related issues are based on the previous announcement (2nd revised) which was sent to you on 7 August 07. The details of construction and the facilities might be changed without prior notice.